# Riot Platforms Ties 96 Percent of Its Leased Megawatts to Anthropic's Ability to Pay

> Riot Platforms' Nov. 4 quarterly report names Anthropic as the tenant of a 15-year, 910 MW Corsicana lease worth $28 billion, and Jason Les targets a first block for June 28, 2027.

- Published: 2026-11-13
- Author: Ryan Elliott Dennis
- Company: Riot Platforms
- Canonical: https://si-infra.com/journal/riot-platforms-anthropic-corsicana-910-mw
- Ledger move: +0.8 Compute (confirmed). Reading after Nov. 13, 2026: 7.5% of the way to superintelligence on the public record.

Riot Platforms named Anthropic PBC as the tenant of its whole Corsicana, Texas campus in a quarterly report filed with the Securities and Exchange Commission on Nov. 4, 2026 [2]. Its press release that morning called the tenant only a leading Frontier AI Lab [1]. The lease runs 15 years, covers 910 megawatts (MW) of critical IT capacity, and carries about $28 billion of rent over the initial term. Two five-year extensions would lift that total to about $54 billion.

Investors spent the next nine days pricing that name. Keefe, Bruyette & Woods (KBW) cut its rating on Riot on Nov. 11 and cited "substantial" reliance on Anthropic, whose own stock listing is expected in the week of Nov. 16 [4]. Data Center Dynamics reported the filing's disclosure on Nov. 12, according to AI Weekly [12]. Riot shares closed at $17.53 on Nov. 13 [5]. So how many of those megawatts exist today?

## Which of Riot's megawatts exist today?

Four megawatt figures describe Corsicana, each with its own date, and one literal frame holds them apart: contracted, energized, approved, delivered.

Contracted comes first. A Riot subsidiary signed the lease for 910 MW on Oct. 28, and it became binding on Nov. 4 after Riot's board approved it and outside consultants signed off on the technical specifications [2]. Energized is the smaller figure: the same filing says Corsicana is equipped today for about 400 MW of developed capacity, which Riot's bitcoin mining machines use.

Approved is the largest figure. Riot's site page lists 1 gigawatt (GW), or 1,000 MW, of fully approved capacity at Corsicana with a direct 345-kilovolt transmission connection [11]. In the 10-Q, Riot Platforms says the planned expansion "was studied and approved by ERCOT under its prior large load interconnection process", a passage FourWeekMBA quotes from the filing [9]. ERCOT is the Electric Reliability Council of Texas, which operates the state's grid.

Delivered is the figure that pays rent. Phase 1 holds 400 MW, with a first block targeted for June 28, 2027 and the full phase for Sept. 11, 2027 [2]. Another 200 MW is targeted for Jan. 28, 2028, and the last 310 MW for July 30, 2028, so Anthropic has yet to receive a megawatt.

## The case for the move: a binding lease on approved power

Jason Les, Riot's chief executive, makes the case for the lease in the release [1]. "With total capital costs of approximately $6 million per IT megawatt, the Corsicana development will require about half the capital of a Tier 3 build while significantly limiting procurement, development, and ongoing operational risk to Riot," Les said. Read the verb "limiting": Les claims a smaller risk for Riot, and the lease moves the rest to the tenant.

How does that transfer work? Riot delivers the land, the power infrastructure and the powered pads, while Anthropic buys, installs, owns and runs the compute modules on those pads and pays the operating costs, power included. Riot's release states the payment rule in one sentence: "Rent is payable on the full 910 MW irrespective of utilization" [1].

Base rent starts at $130 per kilowatt per month and rises 3 percent a year, which is about $1.42 billion a year on the full 910 MW at the opening rate [3]. Riot puts the average at about $1.8 billion a year, beside third-quarter revenue of $181.4 million for the whole company and $18.4 million from data centers [1].

Analysts who favor the deal point to cost and permits. John Todaro of Needham estimates Riot's spending at about $6 million per MW against $11 million to $12 million for a conventional Tier 3 build, and Bill Papanastasiou of Chardan says every power allocation in Riot's portfolio is fully approved [10]. Jefferies upgraded Riot on Nov. 10 and called the Corsicana deal "a reset for the market" [4].

## Why does Anthropic's ability to pay decide the lease's worth?

One tenant now stands behind nearly every megawatt Riot has leased. The 10-Q uses the same defined term for the tenant of Riot's 191 MW Rockdale lease, so Anthropic holds 1,101 of Riot's 1,151 contracted MW, and AMD holds the other 50 [3]. That is about 96 percent by this desk's arithmetic.

Stephen Glagola, the KBW analyst, lowered Riot to Market Perform from Outperform on that concentration, while raising his price target to $23 from $20 [5]. KBW cited the reliance on Anthropic and the lack of investment-grade credit support behind the lease [4]. A 15-year lease is worth what its tenant can pay across those 15 years.

Anthropic's own prospectus shows how much it has promised elsewhere. Global Data Center Hub read the filing and found $482 million of capital spending in the first half of 2026 beside about $321.4 billion of signed leases that had yet to start at June 30 [6]. "So, a 20-year power contract rests on one thing above all: the tenant's ability to keep paying for two decades," Global Data Center Hub wrote. Riot's Corsicana lease runs 15 years, five fewer than the contracts in that sentence, and the same test applies to it.

A Nov. 10 amendment to that prospectus raises the figure, listing about $900.9 billion of computing and other commitments, according to Stock Titan [7]. About $70.7 billion comes due in the year after Sept. 30, 2026, against $131.8 billion of cash and short-term investments on that date. Most of the remainder falls due from 2031 to 2045, which is inside Riot's lease term.

## Who carries the risk until July 2028?

Micah Zimmerman of Bitcoin Magazine read the lease terms in the 10-Q and reached a blunt summary. "The lease puts most of the delivery risk on Riot," Zimmerman wrote [3]. If Riot delivers more than 60 days late, Anthropic earns rent credits, capped at 270 days of base rent for the undelivered blocks, and past 270 days Anthropic can end the lease for that phase on 30 days' notice. Riot's own right to terminate covers uncured payment defaults and bankruptcy.

Money is the second risk. Riot estimates the build at $5.5 billion, or $6 million per MW, and its own share of $2 million per MW comes to about $1.82 billion by this desk's arithmetic, against $950.2 million of cash and bitcoin on Sept. 30 [1]. Les spoke to funding in the release: "That lower capital requirement, combined with our strong balance sheet, means that we do not currently anticipate issuing equity to fund our announced projects." Note the adverb "currently", which dates the pledge to Nov. 4 and leaves later quarters open.

Lenders decide the rest, because Riot owes Anthropic up to $4 million per MW for the modules, about $3.6 billion, and plans to borrow it as project debt sized to the rent. Should that debt prove unavailable on market terms, the 10-Q says Riot "will instead provide rent credits that amortize that amount, plus interest at 12% per year" [2]. Needham says management intends to begin arranging the financing in 2027 [10]. Zimmerman set the measure: "The test for Riot now is whether lenders fund the Corsicana build on terms that keep the 12% clause on paper only" [3].

Texas politics is the third risk, since voters elected Gina Hinojosa governor on Nov. 3 and she takes office Jan. 19 [8]. "When I am governor I will issue a moratorium — a ban — on all data center approvals," Hinojosa said in an Oct. 22 video, with the ban to hold until lawmakers pass protections for Texans. Riot wrote in a risk factor, which FourWeekMBA identified as new, that scrutiny of Texas data centers "could delay or prevent our data center development" [9]. Todaro says management believes Corsicana already holds every approval it needs [10].

## Why is the step 0.8?

Compute moves up by 0.8 on the ledger at confirmed confidence, because an SEC filing names the tenant, the lease is binding, and the site holds 1 GW of approved grid capacity with about 400 MW energized today [2][11]. Riot's 910 MW equals about 9 percent of the ten gigawatts the ledger's definition requires, by this desk's arithmetic.

Three facts hold the step at the bottom of the 0.8 to 1.5 band. Anthropic has yet to receive a megawatt, and the first block is 227 days away. Riot's project debt remains to be arranged, and a single tenant with $900.9 billion of commitments holds 96 percent of the leased megawatts [7].

Against that reading stands the rent clause, the strongest fact the other way: Anthropic owes rent on all 910 MW whatever it uses, and it held $131.8 billion on Sept. 30. Timing answers it. Rent begins within 60 days of each phase's delivery, so the clause binds only as Riot builds, and most of Anthropic's remaining obligations fall due from 2031 to 2045 [1][7]. Les needs lenders in 2027 and a first block on June 28, 2027, while Zimmerman's test goes against Riot the day the 12 percent credits start.

For a reader tracking the buildout, the verdict is to count Corsicana as 910 MW contracted and about 400 MW energized for mining, and credit megawatts to Anthropic's compute only as each block commences.

## By the numbers

- 910 MW: critical IT capacity leased to Anthropic at Corsicana, signed Oct. 28 and binding Nov. 4, 2026 [2].
- About $28 billion of rent over the 15-year initial term, and about $54 billion with both extensions [1].
- $130 per kilowatt per month: starting base rent, rising 3 percent a year [2].
- June 28, 2027: target for the first block of Phase 1, with the full 400 MW due Sept. 11, 2027 [2].
- Anthropic holds 1,101 of Riot's 1,151 contracted MW, about 96 percent by this desk's arithmetic [3].
- 12 percent a year: interest on rent credits if Riot's project financing proves unavailable [2].
- Roughly $900.9 billion: Anthropic's computing and other commitments in its Nov. 10 amended filing [7].
- $950.2 million: Riot's cash and bitcoin on Sept. 30, 2026, against a $5.5 billion build [1].

## What to watch

Project debt for Corsicana, which Needham expects Riot to begin arranging in 2027, is the first test: a loan priced under 12 percent would confirm the move, and rent credits would shrink it. Commencement of the first block on June 28, 2027 would turn contracted megawatts into delivered ones, and a slip past 60 days would start Anthropic's credits. Hinojosa's first orders after Jan. 19 and the result of the state's data center audit, expected in December, will show whether approved sites such as Corsicana stay clear. Anthropic's listing price and its first quarterly report as a public company will show the credit behind 96 percent of Riot's leases.

## Sources

1. Riot Platforms, Inc., "Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights," Riot Platforms, Inc., Nov. 4, 2026, https://www.riotplatforms.com/riot-platforms-reports-third-quarter-2026-financial-results-and-strategic-highlights/
2. Riot Platforms, Inc., "Form 10-Q for the quarterly period ended September 30, 2026," Riot Platforms, Inc., Nov. 4, 2026, https://www.sec.gov/Archives/edgar/data/1167419/000110465926122417/riot-20260930x10q.htm
3. Micah Zimmerman, "Riot (RIOT) Names Anthropic as Tenant in $28 Billion Texas Lease, Could Owe It 12% Interest," Bitcoin Magazine, Nov. 5, 2026, https://bitcoinmagazine.com/news/riot-names-anthropic-texas-lease
4. Prabhjote Gill, "RIOT Stock Sees Downgrade On 'Substantial' Anthropic Reliance: HUT, MARA Shares See Price Target Cuts," Stocktwits, Nov. 11, 2026, https://stocktwits.com/news-articles/markets/equity/riot-stock-sees-downgrade-on-substantial-anthropic-reliance-hut-mara-shares-see-price-target-cuts/cNGDA3PR9B8
5. Nikko Henson, "Is KBW Wrong to Back Off Riot Platforms? Wall Street Still Sees $32," TIKR, Nov. 13, 2026, https://www.tikr.com/blog/is-kbw-wrong-to-back-off-riot-platforms-wall-street-still-sees-32
6. Global Data Center Hub, "Anthropic's IPO Filing Puts $482 Million of Capex Next to $321.4 Billion of Signed Leases," Global Data Center Hub, Nov. 3, 2026, https://www.globaldatacenterhub.com/p/anthropic-ipo-s1-leases-power
7. Stock Titan Editorial Team, "Anthropic IPO Would Value Claude's Maker Between About $917 Billion and $1.02 Trillion," Stock Titan, Nov. 10, 2026, https://www.stocktitan.net/articles/anthropic-ipo-price-range-1-trillion-2026
8. Emily Foxhall, "Gina Hinojosa won the governor's race. What happens to Texas data centers now?," The Texas Tribune, Nov. 4, 2026, https://texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/
9. Gennaro Cuofano, "Riot's 10-Q Names Anthropic as Tenant of $28B Texas Lease," FourWeekMBA, Nov. 4, 2026, https://fourweekmba.com/ai-riots-10-q-names-anthropic-as-tenant-of-28b-texas-lease/
10. Benzinga, "Riot Platforms' 15-Year Powered Land Lease in Texas Adds Construction Efficiency, Election Risk," Benzinga (via KuCoin News), Nov. 5, 2026, https://www.kucoin.com/news/flash/riot-platforms-15-year-powered-land-lease-in-texas-adds-construction-efficiency-election-risk
11. Riot Platforms, Inc., "Corsicana," Riot Platforms, Inc., 2026, https://www.riotplatforms.com/locations/corsicana/
12. Alexis Dufresne, "Riot Platforms names Anthropic as $28B Corsicana tenant," AI Weekly, Nov. 12, 2026, https://aiweekly.co/alerts/riot-platforms-names-anthropic-as-28b-corsicana-tenant

## Images

- ![The Navarro County Courthouse in Corsicana, Texas, seen from the street](https://si-infra.com/img/riot-platforms-anthropic-corsicana-910-mw/1.jpg) The Navarro County Courthouse in Corsicana, Texas, photographed in September 2017; Riot's 910 MW lease to Anthropic covers a 332-acre parcel in the county. (Photo: Michael Barera, Wikimedia Commons, CC BY-SA 4.0, https://commons.wikimedia.org/wiki/File:Corsicana_September_2017_04_(Navarro_County_Courthouse).jpg)
- ![Office building at 7620 Metro Center Drive in Austin, listed by ERCOT as its administration center](https://si-infra.com/img/riot-platforms-anthropic-corsicana-910-mw/2.jpg) The Austin building that ERCOT lists as its executive and administration center, photographed in March 2021; ERCOT approved the 1 GW of grid capacity at Corsicana. (Photo: Larry D. Moore, Wikimedia Commons, CC BY 4.0, https://commons.wikimedia.org/wiki/File:7620_Metro_Center_Drive_Austin_Texas_2021.jpg)
- ![Steel and wood transmission towers carrying 345 kV lines across the North Texas prairie](https://si-infra.com/img/riot-platforms-anthropic-corsicana-910-mw/3.jpg) Transmission towers carrying 345 kV Oncor lines in Clay County, Texas, in September 2019; Riot lists a direct 345 kV transmission connection at Corsicana. (Photo: Jphill19, Wikimedia Commons, CC BY-SA 4.0, https://commons.wikimedia.org/wiki/File:Electric_towers_and_lines_in_Clay_County,_Texas_within_vicinity_of_Bowie,_Texas.jpg)
- ![Gina Hinojosa standing with two fellow Texas state representatives at the 2026 Texas Democratic Convention](https://si-infra.com/img/riot-platforms-anthropic-corsicana-910-mw/4.jpg) Gina Hinojosa with fellow Texas representatives at the 2026 Texas Democratic Convention in June 2026; the governor-elect has pledged a moratorium on data center approvals. (Photo: Pointsoforder, Wikimedia Commons, CC BY-SA 4.0, https://commons.wikimedia.org/wiki/File:Reps._Gonzalez,_Hinojosa,_Howard.jpg)

## Sources

1. Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights (Riot Platforms, Inc., 2026-11-04) https://www.riotplatforms.com/riot-platforms-reports-third-quarter-2026-financial-results-and-strategic-highlights/
2. Form 10-Q for the quarterly period ended September 30, 2026 (Riot Platforms, Inc., 2026-11-04) https://www.sec.gov/Archives/edgar/data/1167419/000110465926122417/riot-20260930x10q.htm
3. Riot (RIOT) Names Anthropic as Tenant in $28 Billion Texas Lease, Could Owe It 12% Interest (Bitcoin Magazine, 2026-11-05) https://bitcoinmagazine.com/news/riot-names-anthropic-texas-lease
4. RIOT Stock Sees Downgrade On 'Substantial' Anthropic Reliance: HUT, MARA Shares See Price Target Cuts (Stocktwits, 2026-11-11) https://stocktwits.com/news-articles/markets/equity/riot-stock-sees-downgrade-on-substantial-anthropic-reliance-hut-mara-shares-see-price-target-cuts/cNGDA3PR9B8
5. Is KBW Wrong to Back Off Riot Platforms? Wall Street Still Sees $32 (TIKR, 2026-11-13) https://www.tikr.com/blog/is-kbw-wrong-to-back-off-riot-platforms-wall-street-still-sees-32
6. Anthropic's IPO Filing Puts $482 Million of Capex Next to $321.4 Billion of Signed Leases (Global Data Center Hub, 2026-11-03) https://www.globaldatacenterhub.com/p/anthropic-ipo-s1-leases-power
7. Anthropic IPO Would Value Claude's Maker Between About $917 Billion and $1.02 Trillion (Stock Titan, 2026-11-10) https://www.stocktitan.net/articles/anthropic-ipo-price-range-1-trillion-2026
8. Gina Hinojosa won the governor's race. What happens to Texas data centers now? (The Texas Tribune, 2026-11-04) https://texastribune.org/2026/11/04/data-center-texas-pause-gina-hinojosa-governor-policies/
9. Riot's 10-Q Names Anthropic as Tenant of $28B Texas Lease (FourWeekMBA, 2026-11-04) https://fourweekmba.com/ai-riots-10-q-names-anthropic-as-tenant-of-28b-texas-lease/
10. Riot Platforms' 15-Year Powered Land Lease in Texas Adds Construction Efficiency, Election Risk (Benzinga (via KuCoin News), 2026-11-05) https://www.kucoin.com/news/flash/riot-platforms-15-year-powered-land-lease-in-texas-adds-construction-efficiency-election-risk
11. Corsicana (Riot Platforms, Inc., 2026) https://www.riotplatforms.com/locations/corsicana/
12. Riot Platforms names Anthropic as $28B Corsicana tenant (AI Weekly, 2026-11-12) https://aiweekly.co/alerts/riot-platforms-names-anthropic-as-28b-corsicana-tenant

Method: https://si-infra.com/method · Ledger: https://si-infra.com/ledger · Founding paper: https://si-infra.com/whitepaper
